Home Dominion Power A Revised Generation Plan Leaves Dominion’s Case For Its Pipeline In Shambles

A Revised Generation Plan Leaves Dominion’s Case For Its Pipeline In Shambles

528
1

by Ivy Main, cross posted from Power for the People VA

In December of last year, regulators at the State Corporation Commission (SCC) took the unprecedented step of rejecting Dominion Energy Virginia’s Integrated Resource Plan (IRP). Among other reasons, the SCC said the utility had over-inflated projections of how much electricity its customers would use in the future.

On March 8, Dominion came back with a revised plan. And sure enough, when it plugged in the more realistic demand projections used by independent grid operator PJM, and accounted for some energy efficiency savings, the number of new gas plants it planned for dropped in half. Instead of 8-13 new gas combustion turbines, the revised plan listed only 4-7 of these small “peaker” units.

Yet there is a good chance Dominion is still overinflating its demand numbers.  Although the re-filed IRP is short and vague, it appears Dominion isn’t figuring in the full amount of the energy efficiency programs it must develop under legislation passed last year.

SB 966 required Dominion to propose $870 million in energy efficiency and demand-response programs designed to reduce energy use and the need for new generation. But Dominion has proposed just $118 million in its separate demand-side management filing (case PUR-2018-00168).

Moreover, the company has concocted a theory whereby it can satisfy that $870 million requirement by spending just 40 or 50 percent of it and pocketing the rest. In its DSM case Dominion argues that since the Virginia Code allows a utility to recover lost revenue resulting from energy efficiency savings, it can simply reduce the required spending by the amount of lost revenue it anticipates.

It’s a great theory, and suffers only from being wrong. (Oh, and also from infuriating legislators, energy efficiency advocates, and pretty much everyone else who was involved in crafting SB 966.)

It also indicates that Dominion’s demand figures in the IRP are based on plans to spend just a fraction of the $870 million in energy efficiency, achieving much less demand reduction than backers of the law envisioned.

If the SCC decides Dominion can’t withhold hundreds of millions of dollars in efficiency spending, that additional spending will have to be factored into demand projections. Thus the IRP’s demand projection can only go down—and with it, the number of gas plants that might be “needed.”

And yet even the resulting number is likely too high. Several of Dominion’s large corporate customers have been trying to leave its fond embrace to seek better renewable energy offerings elsewhere. (The SCC recently rejected Walmart’s effort to defect.) If they were allowed to leave, how much would that further reduce the need for new generation?

For that matter, those customers and many others, including many of the tech companies responsible for what demand growth there is, say they want renewable energy, not fossil fuels. Dominion claims the renewable generation will have to be backed by gas peaker plants, but energy storage would serve the same purpose and further reduce the need for gas. The SCC will rule on that question when—and if—Dominion ever requests permission to build one of those peakers. It is possible the utility will never build another gas plant.

That’s bad news for Dominion Energy’s other line of business, gas transmission and storage. With demand for new gas generation falling off a cliff, Dominion’s ability to rely on its customer base as an anchor client for the Atlantic Coast Pipeline becomes increasingly doubtful.

Dominion may actually have conceded as much in its re-filed IRP. In response to the SCC’s order that Dominion include pipeline costs in its modeling of the costs of gas generation, Dominion merely stated, without discussion, that it is using the tariff of the pipeline owned by the ACP’s competitor Transco, which supplies gas to Dominion’s existing plants.

This statement continues a pattern of Dominion avoiding any mention of the ACP in SCC proceedings, lest it invite hard questions. But Dominion can’t have it both ways. If it will use Transco, it doesn’t need the ACP. If it plans to use the much more expensive ACP and just isn’t saying so, it has lowballed the cost of gas generation and is misleading the SCC.

This is unfair to customers, and it may backfire on Dominion. The ACP received its federal permit on the strength of contracts with affiliate utilities, but Dominion hasn’t yet asked the SCC to approve the deal. Leaving the ACP out of the discussion in the IRP year after year makes it harder to win approval. When and if the company finally asks the SCC for permission to (over)charge ratepayers for its contract with the ACP, it will not have built any kind of a case for a public need or benefit.

This is not just a risk that Dominion Energy chose to take, it is a risk of the company’s own creation. It defied the Sierra Club’s efforts to have the SCC review the ACP contract early on, knowing it would face vigorous opposition from critics. But since then, its chances for approval have only gotten worse. Back then, the pipeline cost estimate came in at $3 billion less than it is today, Dominion Virginia Power was halfway through a massive buildout of combined-cycle gas plants, and the IRP included several more big, new, gas-hungry combined-cycle plants.

Now the ACP’s cost has climbed above $7 billion and may go as high as $7.75 billion, excluding financing costs, CEO Tom Farrell told investors last month in an earnings call. Meanwhile, the IRP includes an ever-shrinking number of gas plants, to be served by a different pipeline.

One investment management company told clients in January the spiraling price tag may make the ACP uncompetitive with existing pipelines. And Farrell faced a host of cost-related questions in his call with investors.

But Farrell downplayed the risk when it came to a question from Deutsche Bank about the need for SCC approval. Managing Director Jonathan Arnold asked, “On ACP, when you guys are talking about customers, does that include the anchor utility customers, your affiliate customers? Does whatever you’re going to negotiate with them need to be approved by the state regulatory bodies?”

Farrell’s answer sounds nonchalant. “In Virginia, it’s like any other part of our fuel clause. It will be part of the fuel clause case in 2021 or 2022 along with all the other ins and outs of our fuel clause.”

Oh, Mr. Farrell, it is not going to be that easy.

An earlier version of this article first appeared in the Virginia Mercury on March 20, 2019.

********************************************************


Sign up for the Blue Virginia weekly newsletter

Previous articleFWIW Virginia: “No Question” New House of Delegates Map “Puts Some Republican Incumbents In a Vulnerable Position – and It Looks Like Their Campaigns Are Ready to Take [That] Seriously”
Next articleGovernor Northam Signs Legislation Increasing Access to Health Coverage for Individuals with Autism